Sedona September and October Road Maintenance Schedule

Article submitted by City of Sedona AZ

Article submitted by City of Sedona AZ

Sedona AZ (September 21, 2016) – The city of Sedona has contracted for milling and paving operations on Sunset Drive and Mountain Shadows Drive starting September 22, 2016, continuing through October 15, 2016. Additionally, a fractured aggregate surface treatment (FAST) will be applied to Pony Soldier Road, and crack sealing will be done throughout the remainder of the Sedona West and Sedona West Number Two subdivisions.

“The repaving of Sunset Drive and Mountain Shadows Drive is part of our annual scheduled maintenance program, while the FAST application is being done as a trial,” said Stephen Craver, city of Sedona engineering supervisor.

FAST is an alternative to a typical mill and overlay that is being explored for residential streets with lower traffic volumes. It provides a similar lifespan as an overlay at a fraction of the cost. “If we receive positive feedback, the FAST application will allow us to maintain more miles of residential streets per year,” added Craver.

Construction activities will generally occur from 6 a.m. to 6 p.m., with traffic regularly restricted to a single lane, causing potential delays. Residents are encouraged to plan ahead, as access to residential driveways will be restricted for up to an hour while Cactus Asphalt applies the fresh asphalt and allows it to cool. On street parking will also be restricted during construction.

adot city construction highwayTraffic control will consist of signage, flagmen and the possible use of pilot vehicles. Motorists are encouraged to reduce speeds through work areas, maintain a safe distance from work vehicles, and be cautious of fresh asphalt, oils, and striping.

Details on each project are below:

Mountain Shadows Drive Paving Project

The repaving of Mountain Shadows Drive will begin approximately 400 feet north of Highway 89A, and continue north to the intersection with Fabulous Texan Way. The construction schedule is as follows:

• Lowering of utility covers will occur on the afternoon of Thursday, September 22, 2016.
• Edge milling will take place on Tuesday, October 4, 2016.
• Thickened roadway edge preparation will start on Thursday, October 6, 2016 and continue through Saturday, October 8, 2016.
• Paving will occur on Wednesday, October 12, 2016.
• Paving may also occur on Thursday, October 13, 2016 if necessary.
• Raising of utility covers will occur on Friday, October 14, 2016.
• Striping will occur on the morning of Saturday, October 15, 2016.

Sunset Drive Paving Project

The repaving of Sunset Drive will begin at the Highway 89A intersection, and continue south to the Shelby Drive intersection. The construction schedule is as follows:

• Lowering of utility covers will occur on the morning of Thursday, September 22, 2016.
• Edge milling will begin on Monday, October 3, 2016.
• Edge milling will continue on Monday night, October 3, 2016 at 10 p.m. near the Highway 89A intersection. This is being done to minimize impacts on the traffic signal during high traffic volume hours. The signal will be in flash mode with a police officer on site.
• Thickened roadway edge preparation on the east side of the roadway will start on Saturday, October 8, 2016 and continue on Monday, October 10, 2016.
• A base treatment will be applied to the segment of roadway between the Shelby Drive intersection and the South Monte Verde Drive intersection on the morning of Monday, October 10, 2016.
• Paving will occur on Tuesday, October 11, 2016, starting at the Highway 89A intersection. Again, the signal will be in flash mode with a police officer on site.
• Paving may also occur on Thursday, October 13, 2016, if necessary.
• Raising of utility covers will occur on Thursday, October 13, 2016.
• Striping will occur on the morning of Saturday, October 15, 2016.

adot construction helmetPony Soldier Road FAST Project

The construction schedule is as follows:

• Application of binder material, fractured aggregate and roadway sweeping will occur on the afternoon of Monday, October 10, 2016.
• A final fog seal application will be applied on Tuesday, October 11, 2016.

Sedona West and Sedona West Number Two Subdivisions Crack Sealing

Crack sealing will occur on Wednesday, October 5, 2016, and Thursday, October 6, 2016, and will consist of the following public roads:

• Johnny Guitar Circle
• Zane Grey Circle
• Zane Grey Drive
• Mogollon Drive
• Broken Arrow Way
• Johnny Guitar Street
• Gun Fury Road
• Fabulous Texan Way
• Flaming Arrow Way
• Stations West Drive
• Last Wagon Drive
• Copper Canyon Drive

For more information on any of these projects, contact Craver at 928-203-5059.

Read www.SedonaEye.com for daily news and interactive views!

Read www.SedonaEye.com for daily news and interactive views!

Leave a Reply

Copyright © 2008-2017 · Sedona Eye · All Rights Reserved · Posts · Comments · Facebook · Twitter ·