Sedona Drainage Project Begins Construction

Sedona AZ (July 17, 2012) – During the week of July 30, 2012, installation of a storm drain pipe system will begin in the Harmony Hills Subdivision in Sedona.

The drain pipe system will begin at the downstream end, east of Navajo Drive, cross the roadway at Windsong Drive and at Lyric Drive, and end north of Lyric Drive. Traffic may be reduced to one lane in each direction if necessary.

The entire construction project is expected to finish mid-December 2012. Local roadway access will remain available during the Harmony Hills project.

The construction work is being performed by Standard Construction Company, Inc. of Avondale, Arizona. This is a City of Sedona project.

If you have questions regarding the project, contact Andy Dickey, Assistant Public Works Director and Assistant City Engineer at 928-203-5039.

For the best Sedona Arizona News and Views? Subscribe to www.SedonaEye.com today.

1 Comment

  1. Liked this story on Facebook.

Leave a Reply

Copyright © 2008-2017 · Sedona Eye · All Rights Reserved · Posts · Comments · Facebook · Twitter ·