Home » General » ADOT I-17 Southbound Climbing Lane Work Begins

ADOT I-17 Southbound Climbing Lane Work Begins

ADOT begins construction on I-17 climbing lane this week

ADOT begins construction on I-17 climbing lane this week

PRESCOTT AZ (January 14, 2013) – Construction to add the first-ever climbing lane to ease traffic flow along a stretch of Interstate 17 south of Camp Verde is set to start this week, according to the Arizona Department of Transportation.

The $11.8 million project will add a third traffic lane in two different areas along southbound I-17 to help move traffic climbing along Copper Canyon Hill near Camp Verde (mileposts 280-287).

One additional lane will be built between the State Route 260 and General Crook Trail traffic interchanges to allow larger vehicles to gain speed before merging while also providing more room for passenger vehicles traveling past slower traffic. Crews also will build a two-mile long climbing lane to improve traffic flow to the top of Copper Canyon.

For the next thirty days, drivers can expect shoulder closures in both directions between AZ SR 260 and General Crook Trail. In addition to the shoulder closures, the truck pull-out at the top of Copper Canyon will be closed for the next six months.

Work hours are Monday through Friday from 7 a.m. until 5 p.m. Drivers should expect intermittent lane closures with minimal delays. The project is scheduled for completion by the end of 2013.

The work zone will be clearly marked by temporary barricades and signage. ADOT advises drivers to allow additional time to reach their destinations and to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.

ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center by calling 5-1-1 and follow the SedonaEye.com daily for construction updates using keyword search “ADOT.”

For the best Sedona Arizona News and Views? Subscribe to www.SedonaEye.com today.

For the best Sedona Arizona News and Views? Subscribe to www.SedonaEye.com today.

3 Comments

  1. Night work for climbing lane project scheduled to begin next week 1/20/13 – Lane restrictions on southbound I-17 expected during work hours.

    Crews will begin overnight work with the set up of temporary concrete barrier on Interstate 17 south of Camp Verde next week, according to the Arizona Department of Transportation.

    Drivers can expect alternating lane restrictions overnight on southbound I-17 between 8 p.m. and 6 a.m. Monday through Friday as crews begin work on the third traffic lane in two separate areas near Camp Verde (mileposts 280-287).

    In addition to lane restrictions at night, crews will be performing work during the daytime near the shoulder that will require intermittent shoulder closures between the hours of 7 a.m. and 5 p.m. through the project work area.

    The work zone will be clearly marked by temporary barricades and signage. ADOT advises drivers to allow additional time to reach their destinations and to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.

    ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule.

  2. Lane closure scheduled Tuesday on southbound Interstate 17 south of Camp Verde – ADOT crews will repair damaged guardrail south of General Crook Trail

    Southbound Interstate 17 just south of Camp Verde (milepost 284) will be narrowed to one lane from 8 a.m. to noon on Tuesday, Jan. 22 not tomorrow as previously mentioned, according to the Arizona Department of Transportation.

    The lane closure will provide a safe work zone for ADOT crews as repair damaged guardrail Minimal delays are expected.

    ADOT advises drivers to proceed through the work zones with caution, slow down, and be alert for construction equipment and personnel.

  3. Lane closure scheduled this week on southbound Interstate 17 – ADOT crews cleaning debris from shoulder Wednesday and Thursday, January 22 and 23.

    Southbound Interstate 17 just north of the McGuireville traffic interchange (mileposts 295-297) will be narrowed to one lane from 8 a.m. to 4 p.m. Wednesday and Thursday, Jan. 23 and 24, according to the Arizona Department of Transportation.

    The lane closure will provide a safe work zone for ADOT crews as they remove debris from the shoulder.

    The speed limit will be reduced to 55 mph and minimal delays are expected. ADOT advises drivers to proceed through the work zones with caution, slow down, and be alert for construction equipment and personnel.