Deck pour and retaining walls underway at Bell and Grand

surprise bell-grand1_original

ADOT Surprise AZ project remains on track for Bell Road to reopen in November 2016

Sedona AZ (August 12, 2016) –  Among all the progress made on a $41.9 million overpass and interchange under construction at Grand Avenue (US 60) and Bell Road, perhaps the most noticeable addition, of late, is the start of retaining walls that will help support the structure.

In addition to continuing to build mechanically stabilized earth walls over the next week, ADOT crews are pouring concrete for the bridge deck.

The Arizona Department of Transportation will close Grand Avenue in both directions from 10:00 p.m. tonight (Friday, August 12), until 5:00 a.m. Saturday, August 13, for the deck pour. During that time, traffic will detour at Dysart and Litchfield roads.

Other work in the coming week includes crews continuing to create new eastbound lanes of Grand Avenue.

Bell Road remains closed in an area between Dysart and Litchfield roads in order to reduce the project’s length and lessen the overall impacts of construction. Access to businesses near the project will be maintained throughout.

adot logoBell Road is scheduled to reopen to traffic by November, while the entire interchange is set for completion by spring 2017.

The primary detour routes while Bell Road is closed are Dysart, Greenway and Litchfield roads. Drivers should observe signs and speed limits. Law enforcement officers are patrolling the area.

Read www.SedonaEye.com for daily news and interactive views!

Read www.SedonaEye.com for daily news and interactive views!

Leave a Reply

Copyright © 2008-2017 · Sedona Eye · All Rights Reserved · Posts · Comments · Facebook · Twitter ·