City of Sedona SR 89A Road Maintenance Schedule

Article submitted by City of Sedona AZ

Article submitted by City of Sedona AZ

Sedona AZ  (June 23, 2016) – Preventative road maintenance on AZ State Highway 89A, between Forest Road and just north of Art Barn Lane, within the city limits of Sedona, will be completed during the week of June 26, 2016. Work will primarily occur from 8:00 p.m. until 7:00 a.m. when traffic is minimal.

The project will seal coat approximately 2,100 feet of existing roadway, along with parking areas and loading zones adjacent to SR 89A. Additionally, all parking bumpers along the highway will be replaced with new decorative recycled rubber car stops.

“This preventative maintenance follows our Uptown Paving Project that was completed last summer, and displays another way we work to provide well maintained and aesthetic streets and parking for our residents and visitors,” said Stephen Craver, Engineering Supervisor, city of Sedona.

Construction will:

  • Seal coat the northbound lane and adjacent parking and loading zones on the evening of Sunday, June 26, 2016, in which northbound traffic will be shifted to the center lane. A flagging operation will occur from Arroyo Roble Drive to past Art Barn Lane. On-street parking on the east side of Highway 89A will be restricted. The following roads and driveways on the east side of Highway 89A will be temporarily restricted for approximately four hours each:
  • Driveway adjacent to 89 Agave: 10 p.m. – 2 a.m.
  • Bus driveway adjacent to Canyon Breeze: 10:30 p.m. – 2:30 a.m.
  • Amara Lane: midnight – 4 a.m.
  • Arroyo Roble Drive: 12:30 a.m. – 4:30 a.m.
  • Art Barn Road: 2 a.m. – 6 a.m.
  • Seal coat the center lane, and the southbound lane between Arroyo Roble Drive to the north end of the project past Art Barn Lane, on the evening of Monday, June 27, 2016. Left turns onto Apple Avenue and Jordan Road will be restricted for approximately four hours.
  • Seal coat the southbound lane from Forest Road to Arroyo Roble Drive, adjacent parking and loading zones, and the Jordan Road intersection on the evening of Tuesday, June 28, 2016. Southbound traffic will be shifted to the center lane. On-street parking on the west side of Highway 89A will be restricted. Access to Apple Avenue and Jordan Road will be restricted for approximately four hours.
  • Survey for new striping during the day of Wednesday, June 29, 2016.
  • Place temporary striping during the evenings of Wednesday, June 29, 2016 and Thursday, June 30, 2016.
  • Place permanent striping and repaint the crosswalks on the evenings of Monday, August 1 and Tuesday, August 2, 2016, after the new seal coat has fully cured.

adot city construction highwayPatrons and merchants are encouraged to plan ahead, as access to and from driveways and parking areas on SR 89A will be restricted for a period of time once the seal coat is applied to allow for dry time.

Portable lights will be used to aid with visibility and safety. Motorists can expect minor delays, and are encouraged to reduce speeds through work areas, maintain a safe distance from work vehicles, and be cautious of fresh oil.

For more information on this project, contact 928-203-5059.

Read www.SedonaEye.com for daily news and interactive views!

Read www.SedonaEye.com for daily news and interactive views!

1 Comment

  1. Weekend Travel Alerts - June 24-26 says:

    Drivers should be aware of the following restrictions:

    Southbound Loop 101 (Pima Freeway) closed between Shea Boulevard and McDonald Drive from 10 p.m. Friday to 5 a.m. Monday
    Southbound Loop 101 (Price Freeway) narrowed to three lanes between Loop 202 and Southern Avenue from 9 p.m. Friday to 9 p.m. Saturday
    Northbound Loop 101 (Pima Freeway) narrowed to one lane overnight at McDonald Drive from 9 p.m. Friday to 5 a.m. Saturday.

Leave a Reply

Copyright © 2008-2017 · Sedona Eye · All Rights Reserved · Posts · Comments · Facebook · Twitter ·