ADOT photoSedona AZ (April 28, 2013) – The construction of the two-mile-long climbing lane near the top of Copper Canyon Hill will require closing Arizona Interstate 17 in both directions on Thursday, May 2, 2013, for up to one hour between midnight and 1 a.m. as crews prepare for blasting rock cuts along the highway.

Traffic on northbound I-17 will be stopped at State Route 169 and southbound I-17 will be stopped at General Crook Trail until the area is reopened.

ADOT urges drivers to adjust their travel schedules or allow extra travel time to reach their destinations.

In addition to the full closures, drivers can expect single-lane restrictions on southbound I-17 through the work zone between mileposts 280-287 for the next three months overnight between 8 p.m. and 6 a.m. Monday through Friday.

Also, a site in the median of I-17 south of AZ State Route 169 has been designated to use for excess materials removed from the project, which will require I-17 to be narrowed overnight to one lane in each direction at mileposts 276-277 as crews enter and exit the highway between 8 p.m. and noon Monday through Friday.

The work zone will be clearly marked by temporary barricades and signage. ADOT advises drivers to allow additional time to reach their destinations and to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.

 

For the best Sedona Arizona News and Views? Subscribe to www.SedonaEye.com today.

For the best Sedona Arizona News and Views? Subscribe to www.SedonaEye.com today.

2 Comments

  1. On May 3, 2013, Geotechnical and Environmental Sciences Consultants Firm, Ninyo and Moore, will be drilling in a couple of locations on Airport Road, about 500-feet north from the Airport Overlook.

    The City of Sedona is working with the Airport Authority and Yavapai County on this matter. The drillings are part of a geotechnical report being prepared by Ninyo and Moore to identify the stability of the area, as part of an approach to repair the road shoulder issue.

    Work is scheduled to begin around 8:00 a.m. and be completed before the end of the business day. Lane restrictions will be in effect, but road will remain open.

    Drivers are asked to please slow down in the work zone, observe flaggers and all traffic control devices.

    Any questions regarding this project can be directed to Andy Dickey, Assistant Public Works Director/Assistant City Engineer at 928-203-5039.

  2. May 9 and 10, 2013 UPDATE: Overnight closures on Interstate 17 south of Camp Verde this week – One-hour closures expected on I-17 in both directions between midnight and 3 a.m.

    Motorists traveling on Interstate 17 south of Camp Verde late Thursday night into early Friday morning, May 9-10, need to plan ahead and allow extra travel time due to overnight construction on a climbing lane project, according to the Arizona Department of Transportation.

    Overnight work will require two, one-hour closures in both directions of I-17 as crews prepare for blasting rock cuts along the highway. The first closure will be from midnight to 1 a.m. and the second closure between 2 a.m. to 3 a.m. Traffic on northbound I-17 will be stopped at State Route 169 and southbound I-17 will be stopped at General Crook Trail until the area is reopened.

    In addition to the full closures, drivers can expect single-lane restrictions on southbound I-17 through the work zone between mileposts 280-287 for the next three months overnight between 8 p.m. and 6 a.m. Monday through Friday.

    Also, a site in the median of I-17 south of State Route 169 has been designated to use for excess materials removed from the project, which will require I-17 to be narrowed overnight to one lane in each direction at mileposts 276-277 as crews enter and exit the highway between 8 p.m. and noon Monday through Friday.

    The work zone will be clearly marked by temporary barricades and signage. ADOT advises drivers to allow additional time to reach their destinations and to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel. The $11.8 million project will add a third traffic lane in two different areas along southbound I-17 to help move traffic climbing along Copper Canyon Hill near Camp Verde (mileposts 280-287). One lane is being built between the State Route 260 and General Crook Trail traffic interchanges to help allow larger vehicles gain speed before merging while also providing more room for passenger vehicles traveling past slower traffic.